Abatement Johnson Hall A
CD's available Monday, January 14, 2013
Scope of Work: Work will include asbestos abatement from Johnson Hall A including, but not limited to, pipe insulation, floor tile and boiler tanks. The building will not be occupied.
Estimated Cost: $400,000.00
Anticipated Start Date: March 4, 2013
Substantial Completion Date: April 14, 2013